Separate a change from the original promise
Start by comparing the requested work with the accepted estimate or contract. A change might add work, remove work or substitute a material. A clarification of included work is not automatically an extra charge. Record the original scope reference and the reason for the proposed change.
Do not use a text saying “go ahead” as a substitute for your jurisdiction’s required contract terms, signatures or disclosures. Licensing, permit and home-improvement contract requirements depend on the location and job. Use your approved local contract process.
Copy this change order checklist
Keep one numbered record attached to the original project. Make the customer-facing description understandable without referring to an internal chat.
| Section | Include | Review question |
|---|---|---|
Reference | Project, original agreement, change number and date | Which accepted scope is being revised? |
Scope delta | Added, removed or substituted work; quantities and location | Could another person identify the work? |
Exclusions | Work not included; unresolved conditions | What would require another review? |
Price delta | Additions, credits, applicable taxes and revised total | Is the net change clear? |
Schedule | Time impact and dependencies; confirmed or provisional dates | What changes and what stays? |
Approval | Required parties, signed version and approval date | Is approval recorded before changed work proceeds? |
Show the arithmetic, including credits
Illustrative numbers only, not market rates: an accepted scope is $4,000. The customer requests a material upgrade adding $600 and removes work worth a $200 credit. The net change is $400 and the revised scope total is $4,400, before any separately applicable tax. A $1,000 deposit already paid remains a payment; it is not another scope credit. If no other amounts are due or paid, the unpaid amount against that total is $3,400.
Itemize additions and removals instead of writing “upgrade: $400.” That makes the reason for the difference auditable. Treat these as an explanation of arithmetic, not an instruction to alter an existing customer price.
Record the schedule impact honestly
A material substitution can change lead time even when installation effort is similar. Record supplier availability, permitting or inspection dependencies and which dates are still provisional. Do not promise a new completion date solely because the customer approved the price.
If conditions uncover potentially unsafe work, stop the affected activity and involve the appropriately qualified professional. This guide does not cover emergency remediation or authorize work outside your license.
Close the loop without deleting history
Save the approved version and communicate the changed scope to the people doing the work. Review the project schedule and future invoice lines against the approved change. Preserve completed work, previous invoices and payment history; an estimate edit should not erase financial evidence.
OptimizeIt connects estimates, projects and scope-led schedules. Review the saved records after changes. Moving has a different Change of Services/BOL process and should not use this contractor checklist as its regulated paperwork.
Official references and limits
Reviewed November 5, 2026. California CSLB: Home Improvement Contracts describes written scope and signed change orders before changed work; this is California-specific, not a nationwide rule. Massachusetts: Home Improvement Contract Sample Language illustrates another jurisdiction’s requirements. Handyman work is not automatically exempt from licensing or permit requirements. This checklist does not determine enforceability, cancellation rights or emergency exceptions; it is a documentation aid, not legal advice.
Frequently asked questions
Can a change order reduce the price?
Yes. Document removed scope and its agreed credit, then show the net change and revised total.
Should a deposit be subtracted from the scope price?
Keep the agreed scope total and payments distinct. A deposit reduces the unpaid balance; it is not a discount or removed-work credit.
Does approval guarantee the new finish date?
No. Supplier, permit, inspection and crew dependencies still need confirmation.
Are change-order requirements nationwide?
No. Check the applicable state and local requirements and your contract.
Should movers use this form?
No. Moving uses its own estimate, Change of Services and BOL requirements.